Science·npcil-project-status PARLIAMENT QUESTION: OPERATIONAL PERFORMANCE OF NPCIL NUCLEAR POWER PLANTS
A parliamentary reply lists the status, expected commissioning dates and revised costs of major NPCIL projects, alongside the Prototype Fast Breeder Reactor and plant-security arrangements.
Prelims pointers
- RAPP-7 began commercial operation on 15 April 2026, while RAPP-8 was in an advanced commissioning stage.
- The RAPP-7&8 project at Rawatbhata has two 700 MW units and a listed twin-unit cost of ₹22,924 crore.
- Kaiga-5&6 are two 700 MW units expected in June 2031 and June 2032, with their ₹21,000 crore cost under revision.
- Kudankulam Units 3&4 and 5&6 comprise four 1,000 MW units with schedules running from June 2027 to March 2030.
- BHAVINI's 500 MW Prototype Fast Breeder Reactor at Kalpakkam is expected to be fully commissioned by March 2027.
PARLIAMENT QUESTION: NATIONAL NUCLEAR MEDICINE EXPANSION PROGRAMME
DAE institutions are expanding nuclear medicine through cancer diagnostics, radionuclide therapies, isotope production, medical-device development and specialised medical training.
Prelims pointers
- BARC provides clinical nuclear-medicine services through centres in Mumbai and Kolkata for cancer diagnosis and therapy.
- VECC operates a 30 MeV medical cyclotron for commercial production of radioisotopes and radiopharmaceuticals.
- Tata Memorial Centre's six-bed high-dose therapy ward was designed under AERB guidelines and includes a sewage delay tank.
- Iodine-131 is used for thyroid cancer, while Lutetium-177 compounds are used for specified prostate and neuroendocrine cancers.
- A dedicated Isotope Production Reactor is being constructed for proposed establishment at BARC, Visakhapatnam.
Environment·tiger-conservation Prime Minister extends greetings on Global Tiger Day, reaffirms commitment to tiger conservation
On Global Tiger Day, Prime Minister Narendra Modi said India is home to almost 70% of the global tiger population and reaffirmed a commitment to science-based conservation, community participation, sustainable development and reduced human-wildlife conflict.
Prelims pointers
- The Prime Minister stated that India is home to almost 70 per cent of the global tiger population.
- India’s tiger-conservation approach was described as science-based and supported by community participation.
- Sustainable development was identified as an element that strengthens tiger conservation.
- Forest personnel, scientists and conservationists were acknowledged for their role in tiger protection.
- The statement linked local-community empowerment with efforts to reduce human-wildlife conflict.
PARLIAMENT QUESTION: YUVIKA (YOUNG SCIENTIST PROGRAMME)
ISRO conducted YUVIKA 2026 from 11–22 May at nine centres for 456 students from 28 states and eight union territories, combining space-science exposure with practical activities and 15% selection weightage for rural and remote students.
Prelims pointers
- YUVIKA 2026 was conducted from 11 to 22 May 2026 at nine ISRO centres.
- The programme included 456 students representing 28 states and eight union territories.
- Participants witnessed a live RH200 rocket launch and interacted with the Bharati Station team in Antarctica.
- The previous edition had 350 students at seven ISRO centres, compared with 456 at nine centres in 2026.
- Selection is merit-based, with 15 per cent special weightage for students from rural and remote areas.
Indian Economy·coal-exchange-rules COAL EXCHANGE RULES
The Coal Exchange Rules, 2026 create a regulated online market for delivery-based coal contracts, with the Coal Controller Organisation overseeing registration, price discovery, surveillance and market safeguards.
Prelims pointers
- The Coal Exchange Rules, 2026 were notified on 4 June 2026 under Section 18B of the MMDR Act, 1957.
- The Coal Controller Organisation is the authority responsible for registering and regulating coal exchanges.
- A coal exchange is defined as an online platform for trading coal, lignite and their processed forms through contracts.
- At least 50% of the Settlement Guarantee Fund must be invested in specified safe or liquid instruments.
- The registration application platform opened on 15 July 2026, with operationalisation estimated within 12 months of application receipt.
Indian Economy·telecom-manufacturing-zone Department of Telecommunications and Government of Madhya Pradesh to Sign MoU for the Establishment of India's First Telecom Manufacturing Zone (TMZ) at Gwalior
The Department of Telecommunications and Madhya Pradesh government are to sign an MoU for Phase I of India's first Telecom Manufacturing Zone at Gwalior, intended to promote domestic telecom-equipment manufacturing, investment, innovation, employment and supply-chain resilience.
Prelims pointers
- Phase I of the Telecom Manufacturing Zone is proposed at Gwalior in Madhya Pradesh.
- The Department of Telecommunications and Madhya Pradesh government are the parties to the MoU.
- The MoU signing was scheduled for 30 July 2026 at Vigyan Bhawan in New Delhi.
- The release describes the proposed Gwalior facility as India's first Telecom Manufacturing Zone.
- The zone is intended to support manufacturers, technology companies, MSMEs and start-ups across the telecom value chain.
Indian Economy·cooperative-grain-storage PROGRESS AND ACHIEVEMENTS OF THE WORLD'S LARGEST GRAIN STORAGE PLAN
Approved on 31 May 2023, the World's Largest Grain Storage Plan in the Cooperative Sector builds PACS-level agricultural infrastructure by converging existing schemes. The release records 1,015 approved projects, 313 constructed godowns and 203 projects under construction.
Prelims pointers
- The grain-storage plan in the cooperative sector was approved by the government on 31 May 2023.
- The plan creates agricultural infrastructure such as warehouses and processing units at the PACS level.
- Its implementation converges existing schemes including AIF, AMI, SMAM and PMFME.
- The annexure reports 1,015 approved projects, 313 constructed godowns and 203 projects under construction.
- Gujarat had 275 approved projects, while Rajasthan had 201 approved projects under the plan.
Indian Economy·white-revolution-2 IMPLEMENTATION OF WHITE REVOLUTION 2.0
White Revolution 2.0 targets 75,000 new Dairy Cooperative Societies in uncovered villages or panchayats and the strengthening of 46,422 existing societies. The release reports 24,097 new societies formed and 31,394 strengthened, alongside dairy infrastructure and NPDD support.
Prelims pointers
- White Revolution 2.0 envisages creating 75,000 new Dairy Cooperative Societies in uncovered villages or panchayats.
- The initiative also targets strengthening 46,422 existing Dairy Cooperative Societies.
- The release reports that 24,097 new DCSs had been formed and 31,394 existing DCSs strengthened.
- Infrastructure support includes bulk milk coolers, automatic collection units, testing equipment and chilling facilities.
- Financial assistance is released through the revised National Programme for Dairy Development of DAHD.
Indian Economy·bharat-taxi-cooperative DRIVERS UNDER BHARAT TAXI
Bharat Taxi is a cooperative-led mobility application operated by the multi-state Sahakar Taxi Cooperative Limited. Officially launched in Delhi-NCR, Gujarat and Maharashtra, it had onboarded 7.97 lakh driver-partners by 19 July 2026 and follows a zero-commission model.
Prelims pointers
- Bharat Taxi is operated by Sahakar Taxi Cooperative Limited, a multi-state cooperative society.
- The mobility platform has been officially launched in Delhi-NCR, Gujarat and Maharashtra.
- A total of 7.97 lakh Sarathis had been onboarded nationwide as of 19 July 2026.
- Under the zero-commission model, no commission is deducted from the fare earned by a Sarathi.
- A separate nominal platform-usage fee supports technology, application maintenance and platform expansion.
Indian Economy·cooperative-societies-status STATUS OF COOPERATIVE SOCIETIES IN INDIA
The National Cooperative Database counted 8,53,430 cooperative societies as of 15 July 2026: 6,62,811 functional, 1,41,442 non-functional and 49,177 under liquidation. Among functional societies, 3,55,680 were profitable and 2,50,442 loss-making.
Prelims pointers
- The National Cooperative Database recorded 8,53,430 cooperative societies as of 15 July 2026.
- The annexure classified 6,62,811 societies as functional and 1,41,442 as non-functional.
- A total of 49,177 cooperative societies were recorded as being under liquidation.
- Among functional societies, 3,55,680 were profit-making and 2,50,442 were loss-making.
- Financial information was unavailable for 56,689 of the functional cooperative societies.
Indian Economy·west-bengal-cooperatives MSCS IN WEST BENGAL
The National Cooperative Database recorded 1,840 Multi-State Cooperative Societies nationally and 73 in West Bengal as of 15 July 2026. The release also details PACS computerisation in West Bengal and the structure of the National Cooperation Policy, 2025.
Prelims pointers
- The National Cooperative Database recorded 1,840 Multi-State Cooperative Societies across India as of 15 July 2026.
- West Bengal accounted for 73 of the Multi-State Cooperative Societies in the national database.
- The PACS computerisation project was expanded from 63,000 to 79,630 PACS nationwide.
- A total of 4,187 PACS in West Bengal had been sanctioned under the computerisation project.
- The National Cooperation Policy, 2025 contains six strategic pillars, 16 objectives and 83 recommendations.
Indian Economy·ncel-organic-exports PROMOTION OF EXPORTS BY NCEL
National Co-operative Exports Limited serves as an umbrella organisation for exporting goods and services, including organic products, made by cooperative societies across India. It has signed an MoU with National Cooperative Organics Limited for certified organic exports under the Bharat Organics brand.
Prelims pointers
- NCEL is mandated to function as an umbrella organisation for exports from cooperative societies across India.
- The export mandate of NCEL covers services as well as goods produced by cooperative societies.
- Organic products are expressly included within the cooperative goods covered by NCEL's mandate.
- NCEL has signed a memorandum of understanding with National Cooperative Organics Limited.
- The NCEL-NCOL memorandum concerns exports of certified organic products under the Bharat Organics brand.
Indian Economy·pacs-computerisation PACS DIGITAL AUTOMATION FRAMEWORK
The PACS computerisation project places functional societies on common ERP-based national software and now covers 79,630 PACS with a ₹2,925.39 crore outlay. The release reports 63,686 PACS onboarded and separately records PACS-level grain storage and NCEL export figures.
Prelims pointers
- The PACS computerisation project was expanded from 63,000 to 79,630 societies with an outlay of ₹2,925.39 crore.
- The annexure reports 65,875 PACS with hardware delivered and 63,686 onboarded on the ERP software.
- The common software includes modules for accounting, statutory audit and management information systems.
- Under the grain-storage plan, godown construction was completed at 313 PACS, creating 1.80 LMT capacity.
- NCEL had exported over 14,89,102 MT of 50 agricultural products valued at ₹5,866.10 crore to 38 countries.
Indian Economy·cooperative-database-states REGISTERED COOPERATIVE SOCIETIES IN JHARKHAND AND GUJARAT
The National Cooperative Database recorded 12,207 cooperative societies in Jharkhand and 88,119 in Gujarat as of 15 July 2026. The release also covers PACS computerisation, NCDC disbursement data and inclusion measures under the 2023 MSCS amendment and PACS model bye-laws.
Prelims pointers
- The NCD recorded 12,207 cooperative societies in Jharkhand and 88,119 in Gujarat as of 15 July 2026.
- The annexure classified 8,141 Jharkhand societies and 79,817 Gujarat societies as functional.
- The national PACS computerisation project was expanded to cover 79,630 PACS with an outlay of ₹2,925.39 crore.
- The MSCS Amendment Act, 2023 provides two board seats for women in every Multi-State Cooperative Society.
- The same 2023 amendment provides one board seat for a Scheduled Caste or Scheduled Tribe member.
Science·nuclear-power-projects PARLIAMENT QUESTION: NUCLEAR POWER PROJECTS
A Lok Sabha reply said three reactors totalling 2,100 MW had begun commercial operation from the 2023–24 construction and commissioning set, while ten reactors totalling 8,000 MW were presently under construction across five states.
Prelims pointers
- KAPP-3 and KAPP-4 at Kakrapar, Gujarat, have 700 MW capacity each and commenced commercial operation.
- RAPP-7 at Rawatbhata, Rajasthan, has 700 MW capacity and commenced commercial operation.
- Ten reactors with a combined capacity of 8,000 MW were reported as presently under construction.
- KKNPP-3 to KKNPP-6 at Kudankulam comprise four units of 1,000 MW each.
- The 2025 SHANTI Act was described as enabling wider participation by private industries and research institutions.
Science·nuclear-energy-mission PARLIAMENT QUESTION: NUCLEAR ENERGY MISSION
The Nuclear Energy Mission targets 100 GW by 2047 through indigenous reactors, wider participation, SMR research and fast-breeder expansion, while recording recent sector milestones.
Prelims pointers
- The Nuclear Energy Mission sets a national nuclear power capacity target of 100 GW by 2047.
- The mission envisages a significant contribution from indigenous Pressurised Heavy Water Reactor technology.
- Pre-project activities have been approved for two 500 MW fast-breeder reactors at Kalpakkam in Tamil Nadu.
- Commercial operation of KAPP-3&4 and RAPP-7 produced a combined nuclear capacity addition of 2,100 MW.
- The Prototype Fast Breeder Reactor attained criticality on 6 April 2026.
PARLIAMENT QUESTION: GAGANYAAN PROGRAMME
A Lok Sabha reply detailed Gaganyaan progress across the human-rated HLVM3, orbital module, crew escape and recovery systems, ground infrastructure, test missions, astronaut training and preparations for the first uncrewed G1 mission.
Prelims pointers
- Development and ground testing of all propulsion stages and structures of the human-rated HLVM3 were completed.
- TV-D1 completed in-flight validation of the Crew Escape System, while TV-D2 was in an advanced stage.
- IADT-01 and IADT-02 used a simulated Crew Module to validate the deceleration system.
- Gaganyatris completed generic training at Glavkosmos in Russia and continued mission-specific training in Bengaluru.
- The indigenous ECLSS is designed to regulate temperature, humidity, pressure and carbon-dioxide levels in the Crew Module.
Geography·ladakh-disaster-mapping PARLIAMENT QUESTION: SPACE TECHNOLOGY FOR DISASTER MANAGEMENT IN LADAKH
A Lok Sabha reply described satellite and geospatial monitoring in Ladakh covering glaciers, glacial lakes, snow, wetlands, waterbodies and landslides, alongside ISRO projects for forecasting, hydrology, GLOF risk and decentralised planning.
Prelims pointers
- A database of more than 2,000 Ladakh glaciers was generated using satellite data from 2020–23.
- The National Hydrology Project inventory covered 3,219 glacial lakes in Ladakh larger than 0.25 hectares.
- GLOF risk modelling was carried out for high-risk glacial lakes including Katkar and Suru.
- The SILAAS project has used satellite data since 2023 to map landslides and generate village-wise alerts in Ladakh.
- SISDP mapped land use, drainage, settlements, slope, rail and road infrastructure at a scale of 1:10,000.
PARLIAMENT QUESTION: OPERATIONAL STAUTS OF NAVIC CONSTELLATION
A Lok Sabha reply said NavIC currently has three satellites providing positioning, navigation and timing services, leaving standalone positioning unavailable because at least four operational satellites are needed, although timing remains functional.
Prelims pointers
- IRNSS-1F completed its stated mission life of ten years before the reported constellation update.
- The three satellites named as providing NavIC PNT services are IRNSS-1B, IRNSS-1I and NVS-01.
- At least four operational satellites in orbit are required to provide basic positioning service.
- NavIC’s standalone positioning service was unavailable, but its timing service remained functional.
- NVS-03 was ready for launch, while NVS-04 and NVS-05 were in advanced stages of realisation.
Science·private-space-sector PARLIAMENT QUESTION: PRIVATE SECTOR PARTICIPATION IN THE SPACE SECTOR
A Lok Sabha reply reported $187 million in space-sector investment during 2026 and 108 IN-SPACe authorisations for non-government entities, while listing policy, finance, infrastructure, skills and technology measures supporting private participation.
Prelims pointers
- IN-SPACe had granted 108 authorisations to non-government entities for various space activities.
- The reply reported total space-sector investment of $187 million during 2026.
- Government support included a ₹1,000 crore Venture Capital Fund and a ₹500 crore Technology Adoption Fund.
- IN-SPACe’s authorisation procedures implement the Indian Space Policy 2023 while considering strategic, security and national interests.
- Seventeen start-ups had been authorised to carry out various space activities.
Science·nuclear-capacity-roadmap PARLIAMENT QUESTION: NUCLEAR POWER GENERATION CAPACITY
India's installed nuclear power capacity was stated as 8,780 MW across 24 plants, with a roadmap for staged expansion to 100 GW by 2047 through NPCIL, other enterprises, private entities and joint ventures.
Prelims pointers
- India's installed nuclear power capacity is 8,780 MW across 24 nuclear power plants.
- Nuclear power contributed about 3.1% of India's total electricity generation in 2025-26.
- RAPP-8 was at 96.26% physical progress in June 2026 and expected to become operational during 2026.
- The roadmap expects nuclear capacity to rise from 8.78 GW to about 22 GW by 2031-32.
- Beyond 2032, NPCIL is envisaged to establish another 32 GW using PHWRs and Light Water Reactors.
Environment·radioactive-waste-management PARLIAMENT QUESTION: RADIOACTIVE WASTES
India regulates radioactive waste through AERB authorisation, differentiated treatment of gaseous, liquid and solid streams, vitrification of high-level waste, environmental surveillance and a closed fuel cycle.
Prelims pointers
- Radioactive solid waste from nuclear plants is typically within 0.15 cubic metres per year per MW.
- The Atomic Energy (Safe Disposal of Radioactive Wastes) Rules, 1987 require AERB authorisation for effluent discharge.
- Gaseous waste treatment includes activated-charcoal adsorption and high-efficiency particulate-air filtration.
- High-level waste from spent-fuel reprocessing is converted into glass through vitrification and stored under surveillance.
- Environmental Survey Laboratories at atomic power plants compare environmental monitoring results with pre-operation radiation baselines.
Indian Economy·deep-tech-growth Innovation, Startups, MSMEs and Quality Manufacturing are Pillars of India's Future Growth: Shri Piyush Goyal at 22nd J.R.D. Tata Memorial Lecture
At the J.R.D. Tata Memorial Lecture, the Commerce Minister linked India's growth strategy to deep technology, startup commercialisation, MSME modernisation, quality manufacturing and wider export market access.
Prelims pointers
- The Minister said a ₹1 lakh crore Research, Development and Innovation Fund would provide long-term, low-cost risk capital.
- Nearly 38,000 GPUs had been onboarded under the IndiaAI Mission for affordable startup and researcher access.
- The second Semiconductor Mission was described as having an allocation of approximately US$12-13 billion.
- The address identified AI, semiconductors, quantum computing, biotechnology, robotics and advanced materials as key frontiers.
- The Minister urged industry to help startups progress from ideas to prototypes and then to commercialisation.
Make current affairs stick
Sign up free to practise current-affairs MCQs with explanations, alongside subject-wise questions and PYQs.