What it’s asking

  1. Assess the potential. Show the size and geography of India's onshore and offshore wind resource against what has been installed.

  2. Explain the concentration. Give physical, economic, infrastructural and policy reasons why wind farms cluster in a few states.

  3. Suggest a way forward. Close with measures that could widen the spatial spread of wind power.

Approach

A 150-word plan you can hold in your head in the exam hall.

  1. Intro~30 words

    Installed capacity and rank against NIWE's assessed potential.

  2. Body~95 words

    Where the potential lies, then physical, economic, grid and policy reasons for clustering.

  3. Conclusion~25 words

    Repowering, hybrids, offshore and transmission to reach the 2030 target.

AI-drafted model answer

Drafted by AI and not yet checked by a person. One way to answer it, not the only one.

Intro
Fourth-largest wind capacity, yet only a small share of NIWE's assessed potential is tapped.
Body
  • Potential: monsoon winds, coast and mountain gaps favour seven states.
  • Offshore Gujarat and Tamil Nadu coasts; wind complements solar at evening peaks.
  • Physical: weak, calm winds in plains and north-east; cyclones on east coast.
  • Economic: best sites occupied by old turbines; land and transport hurdles.
  • Grid and policy: weak evacuation, bidding regime and cheaper solar.
Conclusion
Repowering, hybrid parks, taller hubs, offshore wind and grid corridors can widen the footprint.

Sources: MNRE, Cabinet approval of VGF scheme for offshore wind (PIB, 19 June 2024) · National Wind-Solar Hybrid Policy, 2018 · National Repowering Policy for Wind Power Projects, 2016 · NIWE wind potential assessment at 150 m hub height

Related questions

From the same paper, GS Paper 1, 2022

Write this and get it evaluated

3 free evaluations a month. Write on paper, upload a photo, and see a marks range, notes on your sheet and what to fix.

Loading sign-in options

No card. Model answers stay free.