Nuclear power plants in India: all 24 operating reactors, by station and state

Updated 25 Nov 2026Source: NPCIL plant list (updated to October 2026), Department of Atomic Energy replies in Parliament via PIB

India's operating nuclear fleet is 24 reactors with 8,780 MW of installed capacity at seven stations in six States, according to the Department of Atomic Energy's reply to the Lok Sabha on 29 July 2026 and NPCIL's plant list. This page lists every unit with its reactor type, capacity and commissioning date, ranks the stations by capacity, and sets out the projects under construction and the 2047 target, with an as-of date for each time-sensitive figure.

Installed nuclear capacity, as of 29 July 2026

8,780 MW

24 reactors at seven stations, supplying about 3.1% of India's electricity in 2025-26. The 100 MW RAPS-1 unit is not counted because it is under long-term shutdown.

Installed capacity by nuclear power stationPressurised water (VVER-1000)Pressurised heavy waterBoiling water and heavy water
  • Kudankulam2,000
  • Kakrapar1,840
  • Rawatbhata1,780
  • Tarapur1,400
  • Kaiga880
  • Kalpakkam (MAPS)440
  • Narora440
Values in MW.

Asked in Prelims

3 past questions on this topic, from 1998, 2011 and 2023

GS Paper I, 1995 to 2026.

The 24 units by reactor type

PHWR
20
BWR
2
PWR (VVER-1000)
2

PHWR is pressurised heavy water reactor and BWR is boiling water reactor. The two PWRs are the Kudankulam units. Total 24.

Target for 2047

100 GW

The Nuclear Energy Mission's goal. The roadmap in the DAE's July 2026 reply has 8.78 GW reaching about 22 GW by 2031-32.

Listed as under construction, June 2026

9 units

RAPP-8 (1 x 700 MW), Kudankulam 3 to 6 (4 x 1,000 MW), Gorakhpur 1 and 2 (2 x 700 MW) and Kaiga 5 and 6 (2 x 700 MW).

Oldest units

1969

TAPS-1 and 2 at Tarapur, both boiling water reactors of 160 MW, entered commercial operation on 28 October 1969.

30-second check

Which station has the largest installed nuclear capacity in India?

Show the answer

Kudankulam, Tamil Nadu. Kudankulam has two 1,000 MW units, 2,000 MW in all. Kakrapar (1,840 MW) is next, then Rawatbhata (1,780 MW) and Tarapur (1,400 MW), from the DAE's July 2026 annexure and NPCIL's plant list.

Tap an answer to check

3 real questions

The seven stations, side by side

#Name · Pressurised water (VVER-1000) / Pressurised heavy water / Boiling water and heavy waterMW
01KudankulamTamil Nadu · 2 units of 1,000 MW2,000
02KakraparGujarat · 2 units of 220 MW and 2 of 700 MW1,840
03RawatbhataRajasthan · units 2 to 7, excluding RAPS-11,780
04TarapurMaharashtra · 2 BWR of 160 MW, 2 PHWR of 540 MW1,400
05KaigaKarnataka · 4 units of 220 MW880
06Kalpakkam (MAPS)Tamil Nadu · 2 units of 220 MW440
07NaroraUttar Pradesh · 2 units of 220 MW440

Practise all 11 past questions from Energy, Nuclear and Material Science

Energy, Nuclear and Material Science · every option explained · free

Loading sign-in options

All 24 operating units

NPCIL's list of operating nuclear power units, with capacity and date of commercial operation
Station and StateUnitTypeMWCommercial operation
Tarapur, MaharashtraUnit: TAPS-1Type: BWRMW: 160Commercial operation: 28 Oct 1969
Tarapur, MaharashtraUnit: TAPS-2Type: BWRMW: 160Commercial operation: 28 Oct 1969
Tarapur, MaharashtraUnit: TAPS-3Type: PHWRMW: 540Commercial operation: 18 Aug 2006
Tarapur, MaharashtraUnit: TAPS-4Type: PHWRMW: 540Commercial operation: 12 Sep 2005
Rawatbhata, RajasthanUnit: RAPS-2Type: PHWRMW: 200Commercial operation: 1 Apr 1981
Rawatbhata, RajasthanUnit: RAPS-3Type: PHWRMW: 220Commercial operation: 1 Jun 2000
Rawatbhata, RajasthanUnit: RAPS-4Type: PHWRMW: 220Commercial operation: 23 Dec 2000
Rawatbhata, RajasthanUnit: RAPS-5Type: PHWRMW: 220Commercial operation: 4 Feb 2010
Rawatbhata, RajasthanUnit: RAPS-6Type: PHWRMW: 220Commercial operation: 31 Mar 2010
Rawatbhata, RajasthanUnit: RAPS-7Type: PHWRMW: 700Commercial operation: 15 Apr 2025
Kalpakkam, Tamil NaduUnit: MAPS-1Type: PHWRMW: 220Commercial operation: 27 Jan 1984
Kalpakkam, Tamil NaduUnit: MAPS-2Type: PHWRMW: 220Commercial operation: 21 Mar 1986
Narora, Uttar PradeshUnit: NAPS-1Type: PHWRMW: 220Commercial operation: 1 Jan 1991
Narora, Uttar PradeshUnit: NAPS-2Type: PHWRMW: 220Commercial operation: 1 Jul 1992
Kakrapar, GujaratUnit: KAPS-1Type: PHWRMW: 220Commercial operation: 6 May 1993
Kakrapar, GujaratUnit: KAPS-2Type: PHWRMW: 220Commercial operation: 1 Sep 1995
Kakrapar, GujaratUnit: KAPS-3Type: PHWRMW: 700Commercial operation: 30 Jun 2023
Kakrapar, GujaratUnit: KAPS-4Type: PHWRMW: 700Commercial operation: 31 Mar 2024
Kaiga, KarnatakaUnit: KGS-1Type: PHWRMW: 220Commercial operation: 16 Nov 2000
Kaiga, KarnatakaUnit: KGS-2Type: PHWRMW: 220Commercial operation: 16 Mar 2000
Kaiga, KarnatakaUnit: KGS-3Type: PHWRMW: 220Commercial operation: 6 May 2007
Kaiga, KarnatakaUnit: KGS-4Type: PHWRMW: 220Commercial operation: 20 Jan 2011
Kudankulam, Tamil NaduUnit: KKNPS-1Type: PWR (VVER-1000)MW: 1,000Commercial operation: 31 Dec 2014
Kudankulam, Tamil NaduUnit: KKNPS-2Type: PWR (VVER-1000)MW: 1,000Commercial operation: 31 Mar 2017
NPCIL's list of operating nuclear power units, with capacity and date of commercial operation

The units add up to 8,780 MW, which matches the total in NPCIL's list and in the Department of Atomic Energy's annexure to its Lok Sabha reply of 29 July 2026. The six States are Maharashtra, Rajasthan, Tamil Nadu, Uttar Pradesh, Gujarat and Karnataka. Tamil Nadu has two stations, Kalpakkam and Kudankulam.

Under construction and the 2047 target

Nuclear projects under construction or commissioning, from the Department of Atomic Energy's Lok Sabha reply of 29 July 2026
ProjectCapacityStatus given by DAE (as of June 2026)
RAPP-8, RajasthanCapacity: 1 x 700 MWStatus given by DAE (as of June 2026): 96.26 per cent complete; in advanced stage of commissioning, expected to be operational in 2026
Kudankulam 3 and 4, Tamil NaduCapacity: 2 x 1,000 MWStatus given by DAE (as of June 2026): 82.65 per cent; expected June 2027 and June 2028
Kudankulam 5 and 6, Tamil NaduCapacity: 2 x 1,000 MWStatus given by DAE (as of June 2026): 45.00 per cent; expected June 2029 and March 2030
Gorakhpur (GHAVP) 1 and 2, HaryanaCapacity: 2 x 700 MWStatus given by DAE (as of June 2026): Construction and commissioning in about six years from first pour of concrete, which starts after ground improvement of the nuclear island
Kaiga 5 and 6, KarnatakaCapacity: 2 x 700 MWStatus given by DAE (as of June 2026): Expected June 2031 and June 2032
Nuclear projects under construction or commissioning, from the Department of Atomic Energy's Lok Sabha reply of 29 July 2026
  • The Nuclear Energy Mission aims for 100 GW of nuclear capacity by 2047. The roadmap says the present 8.78 GW should reach about 22 GW by 2031-32, with another 32 GW under NPCIL beyond 2032 using indigenous pressurised heavy water reactors and light water reactors.
  • The Government has approved pre-project activities for two 500 MW fast breeder reactors, FBR 1 and 2, of the same design as the Prototype Fast Breeder Reactor at Kalpakkam. A reply of August 2025 listed the PFBR (1 x 500 MW) as under construction and implemented by BHAVINI.
  • The balance of 45 GW is to come from other public sector enterprises, private sector and joint ventures.
  • The SHANTI Act, 2025 (Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India) received the President's assent on 20 December 2025 and is meant to enable wider participation in nuclear power by the public and private sectors. Under section 1(2) it comes into force on a date the Central Government notifies in the Official Gazette. Once in force, section 91 repeals the Atomic Energy Act, 1962 and the Civil Liability for Nuclear Damage Act, 2010.
  • The Atomic Energy Regulatory Board (AERB) reviews the safety of nuclear power plants, and fuel security is ensured by the Nuclear Fuel Complex, a constituent unit of the DAE.

Key facts

Installed nuclear capacity, 29 July 2026
8,780 MW from 24 reactorsPress Information Bureau, Department of Atomic Energy
Share of electricity generation, 2025-26
About 3.1 per centPress Information Bureau, Department of Atomic Energy
Largest station by capacity
Kudankulam, 2,000 MWNuclear Power Corporation of India Limited
Oldest units
TAPS-1 and 2, boiling water reactors, 28 October 1969Nuclear Power Corporation of India Limited
Reactor types in operation
20 PHWR, 2 BWR, 2 PWR (VVER-1000)Nuclear Power Corporation of India Limited
RAPS-1 (100 MW)
Excluded from the 8,780 MW; under long-term shutdown (August 2025)Press Information Bureau, Department of Atomic Energy
Nuclear Energy Mission target
100 GW by 2047Press Information Bureau, Department of Atomic Energy
SHANTI Act, 2025
Assented 20 December 2025; commences on a notified date; will repeal the Atomic Energy Act, 1962 and the CLND Act, 2010Ministry of Law and Justice, Legislative Department

Asked in Prelims

Real questions on this topic from Prelims 1998, 2011 and 2023. Pick an answer to see every option explained.

Pick an option to check yourself. Every choice gets its own explanation.

Q1SciencePYQ 2023Energy, Nuclear and Material Science

Consider the following statements: Statement-I: India, despite having uranium deposits, depends on coal for most of its electricity production. Statement-II: Uranium, enriched to the extent of at least 60%, is required for the production of electricity. Which one of the following is correct in respect of the above statements?

Show answer

The answer is C.

Why C is right:

Correct. India does rely on coal for the bulk of its electricity despite having uranium reserves. However, nuclear power reactors use low-enriched uranium (about 3-5% U-235), not 60%.

Why not A:

Statement-II is factually wrong; power reactors use low-enriched uranium (3-5%), so it cannot explain anything.

Why not B:

Statement-II is incorrect; nuclear power plants use uranium enriched to only about 3-5%, not 60%.

Why not D:

Statement-I is correct; coal dominates India's electricity mix at over 70% of thermal generation.

Q2SciencePYQ 2011Energy, Nuclear and Material Science

The function of heavy water in a nuclear reactor is to:

Show answer

The answer is A.

Why A is right:

Correct. Heavy water (D₂O) serves as a moderator in nuclear reactors, slowing down fast neutrons to thermal energies so they can sustain the fission chain reaction.

Why not B:

The moderator's purpose is to slow neutrons down, not speed them up.

Why not C:

While heavy water may contribute to heat transfer, its primary role is as a moderator, not a coolant in this context.

Why not D:

Heavy water sustains the chain reaction by moderating neutrons; control rods are used to stop or regulate the reaction.

Q3SciencePYQ 1998Energy, Nuclear and Material Science

Which one of the following statements correctly describes the difference between a nuclear reactor and an atomic bomb?

Show answer

The answer is B.

Why B is right:

Correct. In a nuclear reactor the chain reaction is controlled using moderators and control rods to sustain a steady energy output, whereas in an atomic bomb the chain reaction is uncontrolled and explosive.

Why not A:

Chain reactions occur in both; the difference is in how they are managed.

Why not C:

This is the opposite of reality; the reactor chain reaction is controlled, not uncontrolled.

Why not D:

Both involve chain reactions; in a bomb the reaction is uncontrolled and rapid.

FAQ

How many nuclear power plants does India have?
The Department of Atomic Energy reported on 29 July 2026 an installed nuclear capacity of 8,780 MW from 24 reactors, which sit at seven stations: Tarapur, Rawatbhata, Kalpakkam, Narora, Kakrapar, Kaiga and Kudankulam.
Which is India's largest nuclear power station?
Kudankulam in Tamil Nadu, with two 1,000 MW VVER-1000 units, or 2,000 MW. Kakrapar in Gujarat (1,840 MW) and Rawatbhata in Rajasthan (1,780 MW) follow.
Which nuclear power station has the oldest reactors in India?
Tarapur in Maharashtra has the earliest commercial operation date in NPCIL's list: its two 160 MW boiling water reactors, TAPS-1 and TAPS-2, both entered commercial operation on 28 October 1969.
What is India's nuclear power target for 2047?
100 GW under the Nuclear Energy Mission. The Department of Atomic Energy's roadmap has capacity reaching about 22 GW by 2031-32.
What does the SHANTI Act, 2025 do?
The Sustainable Harnessing and Advancement of Nuclear Energy for Transforming India Act, 2025 received assent on 20 December 2025. It is meant to enable wider participation in nuclear power by the public and private sectors. It comes into force on a date the Central Government notifies, and section 91 then repeals the Atomic Energy Act, 1962 and the Civil Liability for Nuclear Damage Act, 2010.

Sources · Updated 25 Nov 2026